Short facts
- Country:
Germany - Service area:
Overhead line construction
As part of this project, the steel parts on masts 127 and 128 will also be refurbished.
Project overview in figures:
- Project start: September 2022
- Project duration: 09/2022 – 12/2023 (16 months)
- Length of line: 40.6 km
- Steel restoration: Mast 127/128
- Cable assembly: Replacement of conductor cables and insulator chains
- Masts: WA masts: 11, T-masts: 80
This project was carried out in close collaboration with our client, TenneT TSO GmbH, and showcases Cteam's proficiency in renewing high-voltage lines and restoring and maintaining vital infrastructure components. This work helps to ensure a stable and efficient energy supply, guaranteeing that the line will continue to function reliably in the future.
Impressions of the project