Short facts
- Country:
Germany - Service area:
Overhead line construction
The new line will support two systems of TransnetBW GmbH and one system of Amprion GmbH. The work also includes constructing new masts 561A to 572A, as well as laying fibre-optic and ground cables.

Project details:
- Project start:
01.09.2022 - Project duration:
09/2022 – 09/2025 (36 months) - Length of line:
2.7 km - Foundation:
Deep foundation with large bored piles, watertight pit shoring - Total weight of masts:
1360 t / 4000 t CP emergency pylons - Cabling:
Cable pull, regulation of the conductor cables and fibre optic ground cable and fibre optic cable - Special features:
Construction of 17 provisional structures (approx. 4,000 tonnes of CP material) during the construction phase, in challenging mountain locations, provisional structures in FFH areas, marshland and water protection zones.
This project presents the particular challenge of building provisional structures while taking environmental requirements into account, such as soil protection and the protection of FFH areas. This infrastructure measure will help Cteam to strengthen the grid in the Baden Rhine region, ensuring that the area's energy supply remains reliable and efficient in the future.
Impressions of the project