Short facts
- Country:
Germany - Service area:
Overhead line construction
As part of this project, the 220 kV circuit will be dismantled and the foundations and steel parts of mast 127 and 128 will be restored.
Project overview in figures:
- Project start: September 2022
- Project duration: 09/2022 – 12/2023 (16 months)
- Length of line: 40.6 km
- Foundation restoration: Mast 127/128
- Steel restoration: Mast 127/128
- Cable assembly: Replacement of conductor cables and insulator chains
- Masts: WA masts: 11, T-masts: 80
This project was carried out in close collaboration with our client, TenneT TSO GmbH, and showcases Cteam's proficiency in renewing high-voltage lines and restoring and maintaining vital infrastructure components. This work helps to ensure a stable and efficient energy supply, guaranteeing that the line will continue to function reliably in the future.