New build 380 kV line: project Bertikow - Neuenhagen “Uckermark line”

Cteam is carrying out extensive work on the construction of a high-voltage line for our customer, 50Hertz, as part of the “380 kV line Bertikow – Neuenhagen Uckermark line lot 2” project.

Building high-voltage power lines and substation infrastructure, a Cteam construction site with pylons and crane.

Short facts

Country

Germany

Service area

Overhead line construction

Project details

Customer:

50Hertz

Project start:

01.09.2022

Project duration:

09.2022 – 03.2024

Total length:

23.3 km

Foundations:

56 slabs with approx. 7,756 m³ of concrete and 18 deep foundations with bored piles

Total weight of masts:

2,484 tonnes

Cabling:

2 x 3 x 4 264-AL1/34-ST1A with 2 systems, bundle of 4

The project includes the construction of the foundation and mast assembly, pulling the cables, and erecting provisional structures.

High-voltage substation and grid infrastructure construction site with towers, equipment, and overhead lines.

Specific challenges:

  • 110 kV provisional structure for installation of mast 124
  • Crossing protection for the electrified railway line

This ambitious measure will contribute to optimising and expanding the infrastructure in the area of high-voltage lines. Efficient implementation of all safety and environmental requirements ensures that this project is completed successfully and sustainably.

Impressions of the project

Cteam erects a high-voltage power line pylon using a large crawler crane near wind turbines.
Construction site showing rebar and formwork for a foundation, typical for Cteam infrastructure projects.
Overhead power line construction with lattice towers by Cteam Consulting und Anlagenbau.
Cteam constructing a high-voltage power transmission tower foundation and structure.
Cteam Consulting und Anlagenbau experts assemble a high-voltage pylon, connecting renewable energy.
Building high-voltage power lines and substation infrastructure, a Cteam construction site with pylons and crane.
Cteam builds and maintains high-voltage power lines and provides scaffolding solutions.
Overhead line construction by Cteam: installing new high voltage power conductors on transmission tower.